Epoch AI current positive-capacity facilities ranked by estimated total facility MW, with 2025-dollar capex and calculated H100-equivalent compute beside every row.
Datacenters
Planned AI data center capacity
2,715 MW
Microsoft Fairwater Wisconsin ranks first
Facility power
54
Infrastructures ranked
Oct 20
Snapshot recorded
2026 · Checked daily
All 54 infrastructures by facility power
Microsoft Fairwater Wisconsin leads at 2,715 MW; the middle of the board sits at 464.5.
- Ahead of second place
- 265
- Held by the top three
- 18%
- Middle of the board
- 464.5
- Below half the leader
- 45 of 54
Checked against its source every day; the numbers change when the source publishes.
Epoch AI release: 2026-10-20 · 3 checks behind each row · 60% confidence across rows.
| Rank | Name | Facility power | Data center capex 2025 | Data center H100 equivalents | Change | Why |
|---|---|---|---|---|---|---|
| 01 | Microsoft Fairwater Wisconsin | 2,715 MW | $85.73B | 4.5M H100e | This rank | |
| 02 | OpenAI Stargate New Mexico | 2,450 MW | $66.29B | 5.1M H100e | This rank | |
| 03 | Anthropic-Amazon New Carlisle | 2,310 MW | $72.92B | 1.7M H100e | This rank | |
| 04 | Meta Hyperion | 2,203 MW | $61.82B | 4.1M H100e | This rank | |
| 05 | Colossus 2 | 2,065 MW | $58B | 1.8M H100e | This rank | |
| 06 | OpenAI Stargate Shackelford | 1,960 MW | $53.03B | 4.6M H100e | This rank | |
| 07 | QTS Cedar Rapids | 1,587 MW | $42.92B | 3.7M H100e | This rank | |
| 08 | OpenAI Stargate UAE | 1,400 MW | $37.88B | 2M H100e | This rank | |
| 09 | OpenAI Stargate Michigan | 1,383 MW | $37.43B | 2.9M H100e | This rank | |
| 10 | Meta Prometheus | 1,328 MW | $38.72B | 1.2M H100e | This rank | |
| 11 | OpenAI Stargate Wisconsin | 1,300 MW | $34.17B | 2.6M H100e | Showing | |
| 12 | Goodnight | 1,294.1 MW | $38.11B | 2.3M H100e | This rank | |
| 13 | OpenAI Stargate Milam | 1,200 MW | $32.46B | 2.5M H100e | This rank | |
| 14 | OpenAI Stargate Abilene | 1,180 MW | $31.93B | 1M H100e | This rank | |
| 15 | Google Fort Wayne | 1,035 MW | $32.69B | 2.9M H100e | This rank | |
| 16 | Amazon Ridgeland | 1,008 MW | $31.82B | 788.3K H100e | This rank | |
| 17 | Crusoe Abilene Expansion | 941 MW | $25.46B | 1.7M H100e | This rank | |
| 18 | Amazon Madison Mega Site | 819 MW | $25.87B | 514.4K H100e | This rank | |
| 19 | Coreweave Helios | 800 MW | $20B | 638.2K H100e | This rank | |
| 20 | VNET Bayin Ulanqab | 798 MW | $26.52B | 388.1K H100e | This rank | |
| 21 | Envision Galaxy Ulanqab | 612 MW | $17.8B | 169.9K H100e | — | This rank |
| 22 | Meta Bowling Green | 570 MW | $15.99B | 855.2K H100e | 1 | This rank |
| 23 | Huawei Wuhu | 526 MW | $17.31B | 221.9K H100e | 1 | This rank |
| 24 | CoreWeave Ellendale ND | 520 MW | $15.15B | 505.3K H100e | 1 | This rank |
| 25 | STACK Infrastructure NVA02 | 487 MW | $13.18B | 250.6K H100e | 1 | This rank |
| 26 | Google Omaha | 474 MW | $14.96B | 904.5K H100e | 1 | This rank |
| 27 | Meta Montgomery | 465 MW | $13.56B | 407.5K H100e | 1 | This rank |
| 28 | Google Columbus | 464 MW | $14.62B | 576K H100e | 1 | This rank |
| 29 | Anthropic Lake Mariner | 441 MW | $14.32B | 527.1K H100e | 1 | This rank |
| 30 | Huawei Horinger | 414.6 MW | $13.12B | 168.1K H100e | 1 | This rank |
| 31 | QTS Eagle Mountain | 411 MW | $11.52B | 347K H100e | 1 | This rank |
| 32 | AWS New Albany | 405 MW | $12.8B | 351.7K H100e | 1 | This rank |
| 33 | CoreWeave Denton TX | 395 MW | $10.68B | 271.9K H100e | 1 | This rank |
| 34 | Google Storey County | 389 MW | $11.36B | 540.7K H100e | 1 | This rank |
| 35 | Google Lincoln | 339 MW | $10.72B | 672.1K H100e | 1 | This rank |
| 36 | QTS Richmond 3 | 336 MW | $9.09B | 291.1K H100e | 1 | This rank |
| 37 | Google Cedar Rapids | 314 MW | $9.89B | 670.1K H100e | 1 | This rank |
| 38 | Anthropic Barber Lake | 300 MW | $7.84B | 288.5K H100e | 1 | This rank |
| 39 | OpenAI Stargate Lordstown | 300 MW | $8.11B | 545.7K H100e | 1 | This rank |
| 40 | Start Campus Sines Data Campus | 280 MW | $8.83B | 540.7K H100e | 1 | This rank |
| 41 | Meta Los Lunas | 273 MW | $8.26B | 869.1K H100e | 1 | This rank |
| 42 | Stream Phoenix | 267 MW | $8.33B | 160.2K H100e | 1 | This rank |
| 43 | Meta Cheyenne | 249 MW | $7.84B | 236K H100e | 1 | This rank |
| 44 | AWS Berwick | 212 MW | $6.4B | 145K H100e | 1 | This rank |
| 45 | CoreWeave Chester VA | 197 MW | $4.28B | 125.8K H100e | 1 | This rank |
| 46 | Nebius Mantsala | 196 MW | $5.49B | 226.2K H100e | 1 | This rank |
| 47 | Google Red Oak | 185 MW | $5.83B | 279.4K H100e | 1 | This rank |
| 48 | CoreWeave Muskogee OK | 181 MW | $5.8B | 198.1K H100e | 1 | This rank |
| 49 | Vantage TX1 | 179.2 MW | $4.85B | 154.6K H100e | 1 | This rank |
| 50 | Meta Aiken | 168 MW | $4.89B | 147K H100e | 1 | This rank |
| 51 | CoreWeave Lancaster Greenfield site | 124 MW | $3.49B | 232.9K H100e | 1 | This rank |
| 52 | Microsoft Narvik Norway | 124 MW | $3.49B | 265.3K H100e | 1 | This rank |
| 53 | EcoDataCenter 2 | 67 MW | $1.82B | 138.9K H100e | 1 | This rank |
| 54 | Nscale Keflavik | 13.28 MW | $386.78M | 11.6K H100e | 1 | This rank |
Why this rank
OpenAI Stargate Wisconsin on Planned AI Data Center Capacity
Some explanation inputs are unavailable. Not published: the evidence frozen with this snapshot, comparable prior ranking.
Latest future-dated timeline milestone per center after the dataset release date, requiring positive power, capital cost, and H100-equivalent values.
11
Rank on this board
1,300 MW
Score
3
Inputs behind the score
60% confidence · 1 of 1 components evidenced
What the score is built from
1 of 1 evidencedEvery component evidenced · 1 evidence record each
| Component | Value | Contribution |
|---|---|---|
| Data center facility power MW | 1300.0000000000 | 1,300 |
Unchanged since the previous snapshot
No change in rankcomponent_history_unavailable
No component moved since the previous snapshot.
Where each number comes from
3 public recordsFacility capital costData center capex 2025 · observed Oct 20, 2026, 12:00 PM UTC$34.17B60% confidence
- Source
- Epoch AI open datasets
- Grade
- A
- Freshness
- fresh
- Locator
{"rowCount":567,"downloadUrl":"https://epoch.ai/data/data_centers/data_center_timelines.csv","releaseDate":"2026-10-20","contentHashKind":"sha256_raw_bytes","expectedColumns":["Data center","Date","Construction status","Buildings operational","IT power (MW)","Power (MW)","H100 equivalents","Performance (8-bit OP/s)","Total capital cost (2025 USD billions)","Compute cost (2025 USD billions)","Construction cost (2025 USD billions)","Annual operating cost (2025 USD billions)","Water use (MGD)","Current H100 equivalents (from Data center)"],"documentationUrl":"https://epoch.ai/data/data-centers-documentation/downloads","documentationHash":"40bcdc602d20546fb253629beb3f25ee4df294388d5614986572e3d7ef4e1396"}
Facility powerData center facility power MW · observed Oct 20, 2026, 12:00 PM UTC1,300 MW60% confidence
- Source
- Epoch AI open datasets
- Grade
- A
- Freshness
- fresh
- Locator
{"rowCount":567,"downloadUrl":"https://epoch.ai/data/data_centers/data_center_timelines.csv","releaseDate":"2026-10-20","contentHashKind":"sha256_raw_bytes","expectedColumns":["Data center","Date","Construction status","Buildings operational","IT power (MW)","Power (MW)","H100 equivalents","Performance (8-bit OP/s)","Total capital cost (2025 USD billions)","Compute cost (2025 USD billions)","Construction cost (2025 USD billions)","Annual operating cost (2025 USD billions)","Water use (MGD)","Current H100 equivalents (from Data center)"],"documentationUrl":"https://epoch.ai/data/data-centers-documentation/downloads","documentationHash":"40bcdc602d20546fb253629beb3f25ee4df294388d5614986572e3d7ef4e1396"}
H100-equivalent computeData center H100 equivalents · observed Oct 20, 2026, 12:00 PM UTC2,627,589.692 H100e60% confidence
- Source
- Epoch AI open datasets
- Grade
- A
- Freshness
- fresh
- Locator
{"rowCount":567,"downloadUrl":"https://epoch.ai/data/data_centers/data_center_timelines.csv","releaseDate":"2026-10-20","contentHashKind":"sha256_raw_bytes","expectedColumns":["Data center","Date","Construction status","Buildings operational","IT power (MW)","Power (MW)","H100 equivalents","Performance (8-bit OP/s)","Total capital cost (2025 USD billions)","Compute cost (2025 USD billions)","Construction cost (2025 USD billions)","Annual operating cost (2025 USD billions)","Water use (MGD)","Current H100 equivalents (from Data center)"],"documentationUrl":"https://epoch.ai/data/data-centers-documentation/downloads","documentationHash":"40bcdc602d20546fb253629beb3f25ee4df294388d5614986572e3d7ef4e1396"}
More in Datacenters
Operating, under-construction, and planned AI capacity by place and operator.
Reviewed first-party project announcements ranked by disclosed reference amount, with qualifiers preserved and actual spend explicitly separated.
A reviewed first-party project cohort with announced, under-construction, and energized stages plus separately scoped disclosed datacenter and compute MW. Permits and grid queues are never inferred.
See how often AI names you.
Enter your website. In about two minutes, Rank.ai asks ChatGPT, Claude and Gemini 12 questions your customers ask and grades how often they name you.
- Your grade out of 100How often AI names you, cites your site, and how high it ranks you.
- Who gets namedEvery competitor in the answers, most named first.
- The pages AI readsThe sources behind each answer.
- Three fixesWhat to fix first, with a brief for the first article.