Pennsylvania
Data centers, planned capacity, power economics, grid emissions, and AI workforce signals—each tied to a published source and methodology.
- Datasets
- 4
- Latest evidence
- Sep 14, 2026
- Coverage
- Project-level
Planned AI capacity
Latest future-milestone AI data-center facility MW in Epoch AI aggregated by explicit source-provided U.S. state, with facility count, estimated capex, H100e, and owner breadth.
- Published value
- 212 MW
- Evidence N
- 3
- Confidence
- 60%
- As of
- Sep 11, 2026
Industrial electricity economics
Monthly statewide commercial and industrial retail electricity prices for all 50 states and the District of Columbia.
- Published value
- 10.10¢/kWh
- Evidence N
- 3
- Confidence
- 100%
- As of
- Jun 30, 2026
Grid carbon intensity
Generation-based state power-sector CO2e intensity with capacity, generation, and resource-mix context for all 50 states and DC.
- Published value
- 647.871 pounds_per_megawatt_hour
- Evidence N
- 7
- Confidence
- 100%
- As of
- Dec 31, 2023
AI workforce
State employment, concentration, and pay for the exact BLS SOC 15-2051 Data Scientists occupation.
- Published value
- 13,810 jobs
- Evidence N
- 5
- Confidence
- 100%
- As of
- May 15, 2026
Planned AI data centers
| Project | Owner | Planned MW | 2025 CapEx estimate | Milestone | Evidence status |
|---|---|---|---|---|---|
| AWS Berwick1125 Electron Ave, Berwick, PA 18603 | Amazon | 212 MW | $6.4B | Aug 1, 2027 | 60% confidenceEvidence noteBuilding 4 expected to come online around August 2027, judging from prior satellite imagery. Modeled at twice Building 2's capacity because Building 4 is approximately twice its size. |
Planned capacity is estimated, not metered utility load. Planned does not mean permitted, financed, constructed, or energized. Open each project and methodology before using these figures.